N69 Listowel Bypass Proposed Road Development

Works scheduled between July 2022 and Christmas are as below:

Proposed Traffic Management on JBK Road

Phase 1. Works on John B Keane Road between McKennas and Clieveragh Roundabout.

One way traffic E-W between Mckennas and Clieveragh Roundabout.  Ballybunnion traffic diverted down Market St (No left turn onto John B Keane Road).   Works to commence on the 25th July with this phase being completed for the Races on the 16th September 2022.

Phase 2 – Works on Ballybunnion Road/Market St junction

Phase 2 will commence after the races. Two way traffic between McKennas and Clieveragh Roundabout.  One way Traffic in Market St. (N-S).  The Contractor has requested Road Closures at the Ballybunion junction in late November to allow surfacing to be completed.

Phase 3 – Works on Ballygologue Junction

At the same time works will be happening on Ballygologue Junction. One way traffic W-E between Clieveragh Roundabout and Ballygologue. The south side of Ballygologue Rd will be closed, with a closure sought from end September to mid – November.  The Contractor’s programme has this work scheduled for completion by the end of November.

January 2023 through to June 2023 will see works progress for the remainder of the John B Keane Road.   Traffic management for these sections will be finalised in the coming months and having regard to the experience of the works in 2022. 

Newsletter – 4th July 2022 (PDF)
Newsletter – JBK Road July 2022 (PDF)

Original Plans and Route Options

Contact Us
Operations, Capital Infrastucture & Safety,
Room 115
Co.Buildings
Rathass, Tralee,
Co. Kerry
Tel: 066/7183588
Email: [email protected]
Translate »