Tralee Flood Relief Scheme – Notice of Upcoming Path Closures in Tralee

Ground investigations are currently underway in the Tralee area to support the design of the Tralee Flood Relief Scheme.   In order to facilitate these necessary works sections of the Cockellshell Greenway,  Canal Path and River Lee Walkway will need to be closed on public health and safety grounds.  Please note that all public walkways will remain open during the Rose of Tralee festival period (19th – 24rd August inclusive).

Further details of the ground investigation works and the project in general are available on the Tralee Flood Relief Scheme website  www.floodinfo.ie/traleefrs

Path Closures

         

Path Section

Section

Notes

From

To

Work Days

Cockleshell Greenway

A

Path closure required

24/08/2022

30/08/2022

5

Canal Path West
(Blennerville Bridge to Point) 

B

Path closure required

02/08/2022

12/08/2022

8

Canal Path East
(Marina – Blennerville Bridge)

C

        

Path closure required excluding period during the Rose festival period 19-24 August.  Alternative access along N86 footpath

15/08/2022

18/08/2022

4

25/08/2022

03/09/2022

9

River Lee Walkway

D1/D2

Path closure required excluding period during the Rose festival period 19-24 August

25/08/2022

03/09/2022

8