{"id":2692,"date":"2017-10-18T14:28:22","date_gmt":"2017-10-18T14:28:22","guid":{"rendered":"http:\/\/www.kerrycoco.ie\/?page_id=2692"},"modified":"2022-07-21T09:27:44","modified_gmt":"2022-07-21T09:27:44","slug":"n69-listowel-bypass-proposed-road-development","status":"publish","type":"page","link":"https:\/\/www.kerrycoco.ie\/n69-listowel-bypass-proposed-road-development\/","title":{"rendered":"N69 Listowel Bypass Proposed Road Development"},"content":{"rendered":"

[et_pb_section fb_built=”1″ _builder_version=”4.16″ global_colors_info=”{}”][et_pb_row _builder_version=”4.16″ background_size=”initial” background_position=”top_left” background_repeat=”repeat” global_colors_info=”{}” column_structure=”1_4,1_2,1_4″][et_pb_column type=”1_4″ _builder_version=”4.16″ custom_padding=”|||” global_colors_info=”{}” custom_padding__hover=”|||”][et_pb_sidebar area=”et_pb_widget_area_2″ _builder_version=”4.16″ global_colors_info=”{}”][\/et_pb_sidebar][\/et_pb_column][et_pb_column type=”1_2″ _builder_version=”4.16″ custom_padding=”|||” global_colors_info=”{}” custom_padding__hover=”|||”][et_pb_blurb title=”N69 Listowel Bypass Proposed Road Development” _builder_version=”4.17.4″ hover_enabled=”0″ border_style=”solid” use_circle=”off” use_circle_border=”off” global_colors_info=”{}” sticky_enabled=”0″]<\/p>\n

Works scheduled between July 2022 and Christmas are as below:<\/b><\/p>\n

Proposed Traffic Management on JBK Road<\/b><\/p>\n

Phase 1.\u00a0Works on John B Keane Road between McKennas and Clieveragh Roundabout.<\/b><\/p>\n

One way traffic E-W between Mckennas and Clieveragh Roundabout.\u00a0 Ballybunnion traffic diverted down Market St (No left turn onto John B Keane Road). \u00a0 Works to commence on the 25th July with this phase being completed for the Races on the 16th September 2022.<\/p>\n

Phase 2 \u2013 Works on Ballybunnion Road\/Market St junction<\/b><\/p>\n

Phase 2 will commence after the races. Two way traffic between McKennas and Clieveragh Roundabout.\u00a0 One way Traffic in Market St. (N-S). \u00a0The Contractor has requested Road Closures at the Ballybunion junction in late November to allow surfacing to be completed.<\/p>\n

Phase 3 \u2013 Works on Ballygologue Junction<\/b><\/p>\n

At the same time works will be happening on Ballygologue Junction. One way traffic W-E between Clieveragh Roundabout and Ballygologue. The south side of Ballygologue Rd will be closed, with a closure sought from end September to mid – November. \u00a0The Contractor\u2019s programme has this work scheduled for completion by the end of November.<\/p>\n

January 2023 through to June 2023 will see works progress for the remainder of the John B Keane Road.\u00a0 \u00a0Traffic management for these sections will be finalised in the coming months and having regard to the experience of the works in 2022.\u00a0<\/p>\n